Equipping Al-Hartha power station with specialized steel plates from China

Managing the Plate Curtain Steel supply chain from the People's Republic of China to Al-Hartha power station, including conformity inspection to Chinese standards before shipment — boosting the station's capacity and southern power supply.

Project data

Location
Al-Hartha power station, Basra
Completion year
2022
Status
Completed and handed over
Material
Plate Curtain Steel
Country of origin
People's Republic of China
Inspection
Conformity inspection to Chinese standards, pre-shipment
Completion certificate
Available on request

The completion certificate is available on request for prequalification purposes.

Site photography

We do not display generated imagery, and we do not display photographs of projects that are not ours. Photographs of this project will be added from the site archive once documented with date and location.

The documented record

Site photographs for this project are still being gathered from the archive. In the meantime the reference that actually settles a prequalification is the stamped completion certificate — a verifiable document, not an image — and it is available on request.

Completion year
2022
Status
Completed and handed over
Completion certificate
Available on request

The challenge

Specialized material is rejected on arrival if it wasn't inspected at origin — and at that point the problem isn't the material, it's the station's schedule. The difference between a supplier and a supply-chain manager shows up exactly here: who owns conformity, and where is it verified?

The approach

  • We dealt directly with manufacturers in the country of origin rather than buying through an intermediary.

  • We carried out conformity inspection to Chinese standards before shipment — not on arrival, where rejection becomes a delay in the station's schedule.

  • We managed the supply chain from mill to site, including shipping, customs clearance, and inland transport.

The outcome

The plates arrived inspected and conforming, contributing to Al-Hartha's generating capacity for the southern region. This project is our documented reference in international supply chain management.

Request this project's completion certificate

We send this project's completion certificate on request for prequalification purposes. And if you have a project of similar scope, send us the bill of quantities or a scope description and we'll come back with a proposal covering specifications, schedule and price.