Building two model schools in Basra city centre
Two model schools with contemporary architectural design, executed in partnership with Chinese firms, with reinforced concrete skeletons and high-efficiency infrastructure.
Project data
- Location
- Basra city centre
- Completion year
- 2024
- Status
- Completed and handed over
- Buildings
- 2 schools
- Structural system
- Reinforced concrete skeleton
- Delivery
- In partnership with Chinese firms
- Completion certificate
- Available on request
The completion certificate is available on request for prequalification purposes.
Site photography
Photographs from the company's own execution on site, documented with date and location.

The site team at the model-schools project
Basra Governorate2024

Setting up the model-schools site
Basra Governorate2024

Site coordination meeting with the Chinese partner
Basra Governorate2024
The challenge
Building two schools in an established city centre means working within tight site constraints, continuous traffic, and existing buried services — while holding to a design specification prepared abroad and coordinating continuously with a foreign partner operating from a different technical reference.
The approach
We worked in direct partnership with the Chinese firms on matching design details, rather than passing the specification down to a local equivalent.
We executed the reinforced concrete skeletons with quality control and documented lab testing at every pour stage.
The infrastructure for both schools was delivered to high efficiency within the same scope.
The outcome
Both schools were completed in 2024. This brought our record in this building type to five schools in two years, all in Basra.
Request this project's completion certificate
We send this project's completion certificate on request for prequalification purposes. And if you have a project of similar scope, send us the bill of quantities or a scope description and we'll come back with a proposal covering specifications, schedule and price.
We reply Sunday – Thursday, 8:00 – 16:00 Baghdad time
Related projects

Building three model schools in Al-Sadiq district, north Basra
Al-Sadiq district, north Basra2023
Three model schools with reinforced concrete skeletons and modern architectural design to Chinese specification, handed over complete with HVAC and integrated sanitation.
Project details
بانتظار صورة فعلية من الموقع
Building three model schools in Qurna district, north Basra
Building three model schools in Qurna district, north Basra
Qurna district, north Basra2023
Three integrated model schools in Qurna district, executed in partnership with Chinese firms to modern engineering and educational standards, with reinforced concrete skeletons and foundations designed for marshland soil conditions.
Project details