Integrated infrastructure development: paving and sanitation in Ajaydin and Hay Al-Hakim
Sanitation networks, rainwater pumping stations, and modern road paving with high-quality Italian coverings, improving quality of life and traffic movement across two residential areas.
Project data
- Location
- Ajaydin and Hay Al-Hakim, Basra
- Completion year
- 2023
- Status
- Completed and handed over
- Scope
- Paving · sanitation · rainwater pumping stations
- Coverings
- High-quality Italian coverings
- Completion certificate
- Available on request
The completion certificate is available on request for prequalification purposes.
Site photography
Photographs from the company's own execution on site, documented with date and location.

Street 5 — before and after paving
Ajaydin & Hay Al-Hakim, Basra2023

Hay Al-Hakim streets — before and after
Ajaydin & Hay Al-Hakim, Basra2023

Grading and preparing the streets before paving
Ajaydin & Hay Al-Hakim, Basra2023

Levelling with the company's own equipment
Ajaydin & Hay Al-Hakim, Basra2023

Casting concrete kerbs along the streets
Ajaydin & Hay Al-Hakim, Basra2023

Paving with specialised equipment — paver and roller
Ajaydin & Hay Al-Hakim, Basra2023

Laying the sewer line in Hay Al-Hakim
Ajaydin & Hay Al-Hakim, Basra2023

Interlock paving in a residential lane
Ajaydin & Hay Al-Hakim, Basra2023

Ajaydin streets after paving
Ajaydin & Hay Al-Hakim, Basra2023
The challenge
Paving over a new network settles within months if the backfill isn't compacted properly — and then the dispute starts between the network contractor and the paving contractor. Splitting the work between two parties is the cause of the problem, not its consequence.
The approach
We executed the network, compaction, and paving within one scope under one responsibility — so there is no dispute about who owns the first settlement.
Rainwater pumping stations were installed to address water pooling, the hardest problem in Basra drainage.
High-quality Italian coverings were used as the contract specified, not a local equivalent.
The outcome
Completed in 2023 with integrated paving and sanitation across two residential areas, and pumping networks addressing rainwater pooling.
Request this project's completion certificate
We send this project's completion certificate on request for prequalification purposes. And if you have a project of similar scope, send us the bill of quantities or a scope description and we'll come back with a proposal covering specifications, schedule and price.
We reply Sunday – Thursday, 8:00 – 16:00 Baghdad time
Related projects

Completing infrastructure for new streets at Ifraz 35, Hay Al-Hakim
Ifraz 35, Hay Al-Hakim, Basra2024
Delivering the core infrastructure works for the new streets at Ifraz 35, including sanitation networks, rainwater drainage, GIS mapping systems, and water and electricity extensions.
Project details

Building two model schools in Basra city centre
Basra city centre2024
Two model schools with contemporary architectural design, executed in partnership with Chinese firms, with reinforced concrete skeletons and high-efficiency infrastructure.
Project details